Toronto Western Hospital.  Adjacent to the emergency vehicle entrance at Toronto Western Hospital is the power plant building servicing the entire medical facility.  On the roof of the power plant building are 6 cooling towers.  With residences across the street and otherwise surrounding the hospital, these cooling towers were part of Phase 3 of the hospital’s Noise Abatement Action Plan to bring the site into compliance according to MOECC NPC 300.

Project Challenges

Time

The project critical path schedule identified the window for installation of these units to be 2.5 weeks from the end of January into February. This meant that the design had to be spot on, and the installation crew well versed in the intricacies of the project.

Structural Support and Equipment Access.

The custom acoustic plenum silencers had to occupy a small footprint while being easy to traverse. They had to be structurally supported but fully removable allowing access to the towers/motors for regular maintenance. One of the major design challenges was establishing a monolithic system that worked around pre-existing site conditions such as pipes. The final design had to incorporate structural members that could be bolted in after the silencer was in place.

Project Solution

Time

Shipping of 28 silencer sections on eight 48’ trucks over 5 days was staggered to accommodate the installation schedule as well as minimize staging in the limited space.  Parklane worked closely with the site project managers and superintendent to ensure silencer installation activity interfered as little as possible with the running of the hospital.

Design

To accommodate many interferences, an accurate base model of existing site conditions including structural steel was generated (using advanced 3D modelling) and used throughout the silencer design.  Parklane also provided a structural plan allowing the plenum silencer system to be connected to the existing structural frame ensuring that the stub columns were optimally placed on the existing beams.  PMA worked hard to ensure everything lined up and connected soundly on site so as to maintain structural rigidity across the system.

Results

From the commencement of the project, Parklane’s design team worked with the general contractor, site engineers, and hospital representatives to establish a solution that fit the needs of all its stakeholders.  Parklane is committed to delivering valued engineering through acoustic noise abatement solutions. They demonstrated this well throughout their project at Toronto Western Hospital.